Construction Update – August 2016

Aerial image of Parklands Project, August 2016

Aerial image of Parklands Project, August 2016.

Key Activities for August 2016

The following activities were completed in August 2016

  • Civil & Landscaping – Continuation of landscape works within the Main Park. Continuation of turf laying in the oval areas of Main Park. Commencement of the formwork and reinforcement for the abutments to the pedestrian bridge in Main Park.
  • Lot F – Removal of Tower Crane F02. Continuation of window installation across all buildings, continuation of the internal fit out works to all buildings and the commencement of painting on external slab soffits across all Lot F buildings. Commencement of balustrade set out across all Lot F buildings and the passenger lift installation on Buildings F08 and F07.
  • Lot E – Completion of slab on ground and in ground services on Townhouse Lot E02. Commencement of roof framing, gutters and draining and roof insulation and sheeting to Townhouse Lot E05.
  • Lot D – Continuation of window installations and painting of external slab soffits across all Lot D Buildings. Commencement of the passenger lift installation on Building D01 and D05 and balcony tiling across all buildings. Commencement of balustrade set out to Level 4 across all Lot D Buildings.
  • Lot C – Completion of the Level 8 suspended slab of Building C02, Level 7 suspended slab of Building C04 and Level 5 suspended slab on Building C03 are all underway. Commencement of internal fit out works on Building C03 to Level 1. Commencement of set out of External walls and Internal partition walls to Level 4 of Buildings C02 & C04.
  • Lot B – Completion of the Level 6 suspended slab on Building B02 and Level 5 suspended slab on Building B03. Commencement of internal fit out works to Level 1 & 2 on Building B02 and Level 1 on Building B03. Commencement of set out of External walls and Internal partition walls on Building B01.
  • Lot A – Completion of Level 5 suspended slab on Building A01 and Level 4 suspended slab on Building A02. Completion of the installation of Alimak man material hoists on Building A02 and A01.

Key Activities planned in September 2016

  • Lot F – Completion of passenger viagra feminin pas cher lift installation on Buildings F11, F01 and F07. Completion of window installation on Building F01 and F11. Commencement of balustrade post installation and balcony tiling across all Lot F buildings.
  • Lot E – Townhouse Subcontractor commencement of roof framing, gutters, roof drainage and roof insulation to Townhouse Buildings located in E05. Completion of slab on ground and in ground services to E02.
  • Lot D – Dismantle Tower Cranes D01 and D02. Completion of the Building D04 (townhouses) slab on ground and handover to Townhouse Subcontractor. Completion of the passenger lift install on Buildings D03 and D02. Continuation of window installation and painting of balcony soffits and slab edges across all Lot D Buildings. Commencement of balustrade set out to Level 4 across all Lot D Buildings.
  • Lot C – Completion of structure works on Buildings C02, C03 and C04. Commencement of internal fit out works on Level 3 of Building C03 and Level 5 of Buildings C02 and C04.
  • Lot B – Completion of B03 Level 7 suspended slab and Level 7 suspended slab on B02. Commencement of internal fit out works on Level 4 of Building B01, Level 3 of Building B02 and Level 2 of Building B03.
  • Lot A – Completion of Level 7 suspended slab on Building A01 and Level 6 suspended slab on Building A02. Commencement of internal fit out works on Level 3 of Building A01 and Level 2 of Building A02.
DSC00945

Aerial image of Parklands Project, August 2016.